September Project Update - 2020

General:

Location: L2 outdoor court - Ramp

  • Work Task: Construction of the temporary ramp to the West side of the existing ramp. Tenant access/egress through this area will be restricted for duration. Will reopen for tenant use October 16, 2020.
  • Start Date: September 29, 2020 October 5, 2020
  • End Date: October 8, 2020 October 16, 2020
  • Note: Pushed because structural upgrade below needs to be complete first.

Location: McMurray Avenue Landscape

  • Work Task: Removal of landscape required for Hydro PMT removal on October 7. Single lane road closures will be in effect and sidewalk will be closed for duration of work. Miscellaneous demo and landscaping work to also be completed throughout duration. Drive aisle access to Tower off McMurray will be maintained. Loading zone/truck turnaround will be affected.
  • Start Date: September 28, 2020
  • End Date: Feb 2021, 2020
  • Note: This area involves more demo and removal of existing landscape along McMurray Ave. This area will be fenced off from Sept 28, 2020 to Feb 2021. Loud noise associated with demo.

 

Tower:

Location: Tower Autocourt

  • Work Task: Hot rubber roofing. Strong odours.
  • Start Date: August 17, 2020 September 28, 2020
  • End Date: September 11, 2020 October 13, 2020
  • Note: Hot rubber roofing in this area completed to date but will resume once all concrete walls have been poured and stripped.

Location: Landscape @ North Vent Shaft

  • Work Task: Hot rubber roofing. Strong odours.
  • Start Date: October 14, 2020 October 23, 2020 (28
  • days after concrete is poured)
  • End Date: TBD, 2020
  • Note: End date pushed due to pending confirmation on Hydro Duct waterproofing detail.

 

Townhouses:

Location: L1/P1 - East Vestibule

  • Work Task: Building upgrade including abatement and demo work. Restricted access. Appropriate signage will be in place. Emergency exit will be maintained as required.
  • Start Date: October 5, 2020
  • End Date: October 20, 2020