Construction update at Parkview Development in Burnaby, British Columbia

Development Updates

On this page you'll find updates about the ongoing development of the new apartment tower and townhomes at the Parkview Towers site. Updates are posted as we have them, so check back regularly for the latest. 

Return To Blog

May Project Update - 2020

  • Graham’s COVID-19 response can be accessed via hyperlink: Graham's COVID 19 Response
  • Traffic flow changed in the parkade. This will be in place until the end of the project in early 2021.
  • Demolition of the outdoor visitor parking for the Townhouses is complete. 8’ Chain-link fence has been installed around the perimeter of this area.
  • Road closure on McMurray Ave intermittently for Townhouse work; a road closure permit is on file with the City.
  • Level 30 slab pour will be taking place Saturday, May 2nd. A noise variance is on file with the City.
  • Envelope of Tower installed up to Level 23.
  • Crane deliveries are ongoing.
  • Road closures on Hazel Street intermittently for Tower concrete slab pours; a road closure permit is on file with the City.

 

The impact to you:

  • Work will be ongoing on Saturday.
  • Tenant access to parkade limited to McMurray entrance gate.
  • Noise associated with hand tools, concrete vibrators, concrete trucks and pumps ongoing, which will cause increases in noise levels. Monitoring of sound continues to ensure decibel levels set by the City of Burnaby are not exceeded. You will be informed in advance of any work that will go into Noise Variance hours as per City By-laws.
  • Truck traffic on Hazel Street ongoing as concrete pours will continue; traffic control measures are in place.
  • Truck traffic on McMurray Ave ongoing for Townhouse work. Traffic control measures are in place.
  • Sidewalk along Hazel Street and McMurray Ave will be closed while concrete pours are taking place, and as required throughout the duration of the project.