January Project Update - 1

Here's the latest on what's happening:

  • Excavation has begun. Drilling will be happening during this time and may increase noise levels. Excavated material will be hauled out by dump trucks parked along Hazel. Targeted completion of excavation is in the new year (March 2019).
  • Cutting out of the door frame in new wall on P2 will be complete by the end of this week.  Asphalt will be scheduled shortly.
  • One more day of asphalt will take place in the parkade.  Date of this work is unknown at this time.

The impact to you:

  • Dust will be present, a fire hose will be used to keep dust down on the ground level.
  • Noisier work continues. Monitoring of sound continues to ensure decibel levels set by the City of Burnaby are not exceeded.
  • Increased truck traffic will continue, traffic control measures are in place.
  • Sidewalk along Hazel Street will be closed while demolished material is loaded into dump trucks and will be reopened after hours.