February Project Update - 1

Here's the latest on what's happening:

  • Excavation will continue. During this time, drilling is taking place and and there will be¬†increased noise levels. Excavated material will be hauled out by dump trucks parked along Hazel. Targeted completion of excavation is near the end of March.
  • One more day of asphalt will take place in the parkade. The date for this is tentatively set for Saturday, Februrary 23rd.

Impact to you:

  • Dust will be present, a fire hose will be used to keep dust down on the ground level.

  • Noisier work continues. Monitoring of sound continues to ensure decibel levels set by the City of Burnaby are not exceeded.

  • Increased truck traffic will continue, traffic control measures are in place.

  • Sidewalk along Hazel Street will be closed while excavation is taking place.