Construction update at Parkview Development in Burnaby, British Columbia

Development Updates

On this page you'll find updates about the ongoing development of the new apartment tower and townhomes at the Parkview Towers site. Updates are posted as we have them, so check back regularly for the latest. 

Return To Blog

August Project Update 2020

Here is the latest:

  • Location: Hazel St. Sidewalk
    • Work Task: Topsoil and shotcrete removal. Loud noise associated with the chipping of shotcrete.
    • Start Date: August 10, 2020
    • End Date: August 26, 2020
  • Location: Tower Autocourt
    • Work Task: Hot rubber roofing. Strong odours.
    • Start Date: August 17, 2020
    • End Date: August 25, 2020
  • Location: Landscape @ North Vent Shaft
    • Work Task: Scan/drilling for lamination and concrete pour. Noisy work associated with drilling.
    • Start Date: August 10, 2020
    • End Date: August 28, 2020
  • Location: P2 - South Vestibule
    • Work Task: Building upgrade including abatement and demo work. Restricted access.
    • Start Date: July 27, 2020; @ 7:00am -
    • 3:00pm during weekdays
    • End Date: Approx. August 21, 2020