July Project Update – 2

Here's the latest on what's happening: Level P3 is now complete. Level P2 suspended slab complete and P2 walls/columns are ongoing. Level P1 deck to be installed this week. Level P1 steel deliveries arrrived, Monday, July 15. Crane deliveries are ongoing. Road closures on Hazel Street intermittently for concrete slab pours; road closure permit has been…

Read More

July Project Update – 1

Here's the latest on what's happening: Level P3 suspended slab completely poured. P3 walls/columns are being poured. Level P2 suspended slab and P2 walls/columns are ongoing. Crane deliveries are ongoing. Road closures on Hazel Street intermittently for concrete slab pours; we have a road closure permit with the City. We will apply for Noise Variances…

Read More

May Project Update – 1

Here's the latest on what's happening: Level P4 Parkade concrete slab preparation is ongoing for the next couple weeks. Concrete pouring of slab to follow. Parkade footings and verticals (columns and walls) are being poured. Mechanical and Electrical underground piping being installed. Crane activity ongoing. The impact to you: Noise associated with hand tools, concrete…

Read More

April Project Update – 2

Here's the latest on what's happening: Detailed excavation and concrete pouring is ongoing. Excavated material is currently being stockpiled until haul-out occurs. P4 Slab on grade preparation is ongoing (laying of gravel) for the next few weeks. Concrete pour will follow. Parkade footings and verticals (columns and walls) are being poured. Crane activity ongoing. Excavator will be…

Read More

April Project Update – 1

Here's the latest update: Detailed excavation and concrete pouring of the strip footings is ongoing. Excavated material will continue to be hauled out by dump trucks parked along Hazel. Drilling will be completed April 17, 2019 and the drill rig is scheduled to be removed shortly afterwards. Crane has been erected. Excavator will be removed…

Read More

March Project Update – 4

Here's the latest update: Excavation to be complete within the week and drilling will stop. Excavated material will continue to be hauled out by dump trucks parked along Hazel. Detail excavation of the footings will start imminently. Crane erection is officially scheduled for April 3 to April 5, 2019. This will take 3 days from…

Read More

March Project Update – 3

Here's the latest on what's happening: Excavation will continue. Drilling taking place and increased noise levels will happen during this time. Excavated material will be hauled out by dump trucks parked along Hazel. Targeted completion of excavation is near the end of March. Crane erection is scheduled for first week of April 2019. This will…

Read More

March Project Update – 2

Here's the latest on what's happening: Excavation will continue. Drilling taking place and increased noise levels will happen during this time. Excavated material will be hauled out by dump trucks parked along Hazel. Targeted completion of excavation is near the end of March. Asphalt in the parkade is complete.  Cleaning to take place Friday, March…

Read More

March Project Update – 1

Here's the latest on what's happening: On Saturday March 2nd Graham will be asphalting the P2 parkade in Tower 1. They will be setting up in the parkade and be bringing in the asphalt with a bobcat to P2. This work will start at 9:00am. Impact to you: There will be some traffic delays (ramp to…

Read More

February Project Update – 1

Here's the latest on what's happening: Excavation will continue. During this time, drilling is taking place and and there will be increased noise levels. Excavated material will be hauled out by dump trucks parked along Hazel. Targeted completion of excavation is near the end of March. One more day of asphalt will take place in the…

Read More