January Project Update 2 – 2020

Here's the latest update: Traffic flow changed in the parkade. This will be in place until the end of the project in early 2021. Demolition of the outdoor visitor parking for the Townhouses is ongoing. 8’ Chain-link fence has been installed around the perimeter of this area. Level 18 slab pour will be taking place…

Read More

January Project Update – 2020

Here is the latest update: Traffic flow changed in the parkade. This will be in place until the end of the project in early 2021. Demolition of the outdoor visitor parking for the Townhouses is ongoing. 8’ Chain-link fence has been installed around the perimeter of this area. Townline has erected their new crane at…

Read More

December Project Update – 2019

Here is the latest update: Traffic flow in the parkade to change the morning of Friday December 20th. Graham will put up signs closing off outdoor visitor parking and entrance gate at Tower B. Tenants will have access to parkade through McMurray gate only. Demolition of the outdoor visitor parking for the Townhouses has begun.…

Read More

November Project Update 2019 – 2

Here is the latest update: L11 concrete slab pour on this Friday, November 29, 2019. New hoarding at Townhouse area to be installed December 2, 2019. Old hoarding will be removed, opening the ramp in parkade. Graham will put up signs closing off outdoor visitor parking and entrance gate at Tower B. Residents will have…

Read More

November Project Update

Here's the latest on what's happening: A material hoist will be installed on November 15th. The hoist will be placed on the west side of the building. This upcoming Sunday, between 9 am and 3 pm, the Fire Department will conduct a tower-crane rescue exercise. The impact to you: Once the material hoist is installed,…

Read More

October Project Update – 2

Here's the latest on what's happening: L5 vertical concrete poured on Monday (Oct 21) Fly tables to Level 6 (Oct 22) Trade layout and bottom rebar install on Level 6 (Oct 23) Trade rough-in and top rebar install on Level 6 (Oct 24) Pour Level 6 slab (Oct 25) Work will be taking place Saturday,…

Read More

October Project Update

Here's the latest on what's happening: L3 deck (first typical floor) concrete pour completed (Oct 4) L3 vertical started yesterday, Monday (Oct 7) L4 tables started today, Tuesday (Oct 8) Reshoring of parkade and above grade slabs ongoing Crane deliveries are ongoing Road closures on Hazel Street intermittently for concrete slab pours; we have a…

Read More

September Project Update

Here's the latest on what's happening: L2 deck concrete pour is today L2 vertical to start tomorrow (Sept 24) L3 tables to start Wednesday (Sept 25) Work will be taking place Saturday, September 28th Re-shoring of parkade slabs below ongoing Crane deliveries are ongoing Road closures on Hazel Street intermittently for concrete slab pours; a…

Read More

August Project Update – 2

Here's the latest on what's happening: L1 Transfer slab rebar installation ongoing L1 Transfer slab trade rough-in and layout ongoing Reshoring of parkade slabs below ongoing Transfer slab: 1st pour scheduled for 24Aug19, 2nd pour on 27Aug19; Hazel Street will be closed and will require noise variance with the City of Burnaby Crane deliveries are…

Read More

July Project Update – 3

Here's the latest on what's happening: We will have a large concrete pour on Saturday, August 17th that will begin at 6:00 am. Graham Construction will be getting a noise variance for this work. This pour is for the ground floor. The impact to you: While this work is being completed, noise levels will unfortunately be…

Read More