August Project Update – 1

Here's the latest on what's happening: P1 core and South foundation walls poured Tuesday, 30Jul19 P1 Emergency generator delivered Wednesday, 31Jul19 P1 West foundation wall poured Wednesday, 31Jul19 P1 divider wall core to be poured Thursday, 01Aug19 L1 slab formwork ongoing L1 trade layouts ongoing L1 slab rebar install starting 06Aug19 for 2 weeks Level…

Read More

June Project Update 4 – 2020

Tower: – Windows to be installed to L28, July 3rd. – Precast Panels to be installed to L29, July 3rd. – Level 1 Autocourt scanning/drilling ongoing all week. – Tower balcony guardrail install all week. – Balcony painting all week. – Crane deliveries are ongoing. – Road closures on Hazel Street intermittently for Tower deliveries; a road…

Read More

June Project Update 3 – 2020

Tower: – Level 34 (Machine Room Roof) pour rescheduled for Tuesday, June 23rd. – Windows to be installed to L27, June 26th. – Precast Panels to be installed to L28, June 26th. – Tower balcony guardrail install all week. – Balcony painting all week. – Level 1 Autocourt surface demo ongoing. Scanning/Drilling starting June 22nd. -…

Read More

June Project Update 2 – 2020

Here is the latest update: Level 34 (Machine Room Roof) pour is scheduled for Thursday, June 18th. Envelope of Tower installed up to Level 27/28 this week. Tower balcony guardrail install this week. Dogwash door demo in existing parkade P1 to start June 22nd Level 1 Autocourt surface demo ongoing. North and South facing balcony…

Read More

June Project Update – 2020

Here is the latest update: – Level 1 Autocourt surface demo ongoing. – Level 33 (Mechanical Roof) pour is scheduled for Wednesday, June 10th. – Envelope of Tower installed up to Level 26/27. – North and South facing balcony soffits are being painted. – Asphalt work at the exterior of Tower 2 East Exit will be…

Read More

May Project Update 2 – 2020

Here is the latest update: Traffic flow changed in the parkade. This will be in place until the end of the project in early 2021. Demolition of the outdoor visitor parking for the Townhouses is complete. 8’ Chain-link fence has been installed around the perimeter of this area. Road closure on McMurray Ave intermittently for…

Read More

May Project Update – 2020

Graham’s COVID-19 response can be accessed via hyperlink: Graham's COVID 19 Response Traffic flow changed in the parkade. This will be in place until the end of the project in early 2021. Demolition of the outdoor visitor parking for the Townhouses is complete. 8’ Chain-link fence has been installed around the perimeter of this area. Road…

Read More

April Project Update 2 – 2020

Here's the latest on what's happening: Graham Construction's COVID-19 commentary can be accessed via this hyperlink: Graham's COVID 19 Response The next crane jump is scheduled for April 17, 18, and 20. Hazel Street will be closed for the entirety of these days Traffic flow changed in the parkade. This will be in place until the…

Read More

April Project Update – 2020

Here is the latest update: Graham Construction’s COVID-19 response is here: Graham's COVID 19 Response. The next crane jump is scheduled for April 17, 18, and 20. Hazel Street will be closed for the entirety of these workdays. Traffic flow changed in the parkade. This will be in place until the end of the project in…

Read More

March Project Update – 2020

Here is the latest update:   Traffic flow changed in the parkade. This will be in place until the end of the project in early 2021 Demolition of the outdoor visitor parking for the Townhouses is ongoing. 8’ Chain-link fence has been installed around the perimeter of this area Road closure on McMurray Ave intermittently for Townhouse…

Read More