  • Location: McMurray Ave.
    • Work Task: The offsite sidewalk along the South end of McMurray Ave will be replaced.
    • Start Date: March 5, 2021 End Date: TBD
  • Location: McMurray Ave
    • Work Task: The offsite sidewalk along the North end of McMurray Ave will be replaced.
    • Start Date: March 29, 2021 End Date: TBD
  • Location: Grange Street
    • Work Task: The offsite sidewalk along Grange Street will be replaced. Start Date: April 12, 2021 End Date: TBD