December Project Update 2020-2

  |     |   Project Updates

1. Location: Tower 1 – Stairwell P2 to L18

  • Work Task: Scanning, coring and pipe install in existing stairwell for Sprinkler work. Loud noise associated with coring and pipe install.
  • Work sequence and associated dates: a) Scanning – Completed; b) Coring – January 6 to January 11, 2021 3) Pipe Install – TBD closer to date

2. Location: Landscape work at McMurray and Hazel Ave

  • Work Task: Miscellaneous landscape work. Graham Construction's fencing will be installed and will take over a portion of the existing loading zone on McMurray Ave.
  • Start Date: January 4, 2021