December Project Update 2020

  |     |   Project Updates


 

 

DATE

WORK

ACCESS & LOADING IMPACT

  1.  

Dec 7, 2020 – Dec 11, 2020

Removing all trees and plant cover in the green “Graham’s Fenced Work Area” shown

  • Residents need to exit in the paths
  • No impact on loading area shown in yellow
  1.  

Dec 14, 2020 – Jan 8, 2021 (tentative, see note below)

Removing all hardscape and soil from the green “Graham’s Fenced Work Area”

  • Residents need to exit in the paths shown
  • Fencing will be extended into the yellow “Extending Loading Zone” slightly reducing loading area as shown
  1.  

Jan 11, 2021 onwards (tentative, see note below)

  • Civil contractor will begin the new sidewalk, bike lane and planter installation
  • Graham will begin building the new stairs and pathway to McMurray from Tower 1 within the green zone
  • East wall of the loading bay, where the blue fence line is, will stay as a permanent change.

 

NOTE: The City of Burnaby recently issued a blanket notice not permitting street closure during Christmas break between December 14th and January 4th, but an appeal has been submitted to the City to allow street closure for construction during this period to stay on schedule as per the above.

In the event that the attempt to appeal is unsuccessful, the start of the 2nd activity shown above will be delayed to January 4th, and the 3rd activity will be pushed out accordingly.