Tower 2 (Tower B) – Grange Street Stairs

  • Demo of existing retaining wall at stairs to allow for membrane tie-in between lamination slab and existing. Loud noise and vibration associated with demo work sporadically throughout duration of work. Access/egress to existing stair case and Tower
  • 2 East entrance will be maintained and restricted during work hours only.
  • Start Date: November 30, 2020
  • End Date: February 2021

Tower 3 (Tower C) – Parkade P3 to P1

  • Traffic coating throughout new parkade. Strong odours will be noticeable throughout existing parkade. Appropriate ventilation measures will be put in place.c
  • Start Date: December 7, 2020
  • End Date: Feb 2020

 