November Project Update – 2020

  |     |   Project Updates

General:

Location: L2 outdoor court – Ramp

  • Work Task: Construction of the temporary ramp to the West side of the existing ramp. Residents will be able to use the new ramp as of November 5, 2020

Location: L2 outdoor court – Landscape Removal/Demo

  • Work Task: Existing landscape to be removed and structural demo to follow. Demo noise throughout duration.
  • Start Date: November 5, 2020
  • End Date: TBD

Location: L1/P1 – Tower A South Vestibule

  • Work Task: Building upgrade including abatement and demo work. Restricted access. Appropriate signage will be in place. Emergency exit will be maintained as required.
  • Start Date: November 23, 2020
  • End Date: TBD