August Project Update 2020

  |     |   Project Updates

Here is the latest:

  • Location: Hazel St. Sidewalk
    • Work Task: Topsoil and shotcrete removal. Loud noise associated with the chipping of shotcrete.
    • Start Date: August 10, 2020
    • End Date: August 26, 2020
  • Location: Tower Autocourt
    • Work Task: Hot rubber roofing. Strong odours.
    • Start Date: August 17, 2020
    • End Date: August 25, 2020
  • Location: Landscape @ North Vent Shaft
    • Work Task: Scan/drilling for lamination and concrete pour. Noisy work associated with drilling.
    • Start Date: August 10, 2020
    • End Date: August 28, 2020
  • Location: P2 – South Vestibule
    • Work Task: Building upgrade including abatement and demo work. Restricted access.
    • Start Date: July 27, 2020; @ 7:00am -
    • 3:00pm during weekdays
    • End Date: Approx. August 21, 2020